Shift summary day shift 1-25-00


Subject: Shift summary day shift 1-25-00
From: Vivian O'Dell (odell@fnal.gov)
Date: Fri Feb 04 2000 - 15:40:25 CST


Shift summary for day shift 1-25-00

 8:00 am Walk through. All o.k.. Checked that the compressors for the
           chiller are on. Surveyors are working in the hall.

           For safety during this down time, I removed the cable that sends
           the ramping signal to DC HV, and set trip current on all Droege
           channels to 10 uA.

 2:00 pm Walk through. All o.k.. Performed gas shift check list.
           Chiller compressors are still on.

-hogan