dec 9,1999 day shift summary

arenton@uvahee.phys.virginia.edu
Thu, 9 Dec 1999 16:44:28 -0500

Shift Summary for day shift, 12/09/99

On Shift: Hogan N (first half) Mike A (second half)

Hours of beam delivered at all intensities:0
Hours of beam delivered at nominal intensity:
Hours of E832 data (special runs not included):
Hours of special runs (laser scans, muon runs...):

Accounting of lost time: magnet replacement etc.

===============================================================

Runs ended this shift: none

===============================================================

Accesses during shift: open access

Doug will start vacuum pumpdown later this evening, the hall
needs to be locked up for 8 hours when that starts

===============================================================

Description of Shift:

Surveryors working most of the day in the hall

Rick K looking at noise on cables for KAMI test.

trigger 1 skim processing continues.