Shift Summary for Evening 10/30

S. Elizabeth Turner (eturner@cooper.physics.ucla.edu)
Sat, 30 Oct 1999 17:04:09 -0700 (PDT)

Shift Summary for Evening shift, Oct 30, 1999

On Shift: Elizabeth

Hours of beam delivered at all intensities: 0
Hours of beam delivered at nominal intensity: 0
Hours of 99 data (special runs not included): 0
Hours of special runs (laser scans, muon runs...): 0

Accounting of lost time:

No beam this shift due to TeV studies.

Activities:

16:30 BobT begins DAQ debugging. Not a lot of progress
made before we learn of tonight's power outage.

18:00 Do Gas Checklist

18:15 POWER OUTAGE will be tonight at 22:00. Begin
powering down all systems.

19:00 All systems powered down.

19:05 Everyone goes home.

Note: There will be another power outage tomorrow evening
or Monday morning. The exact time of that outage will be
decided at noon tomorrow.