Shift Summary - Day - Oct 5, 99 - Machine Off

Douglas A. Jensen (djensen@fnal.gov)
Tue, 5 Oct 1999 15:35:06 -0500 (CDT)

Shift Summary for DAY shift, 10/05/99

On Shift: H. White, D. Jensen

Hours of beam available at all intensities: 0.00
Hours of beam available at nominal intensity: 0.00
Hours of E799 data (special runs not included): 0.00
Hours of special runs (laser scans, muon runs...): 0.00

Accounting of lost time:
He Purification in progress at TeVatron.
========================================================================
Runs ended this shift:
Tapes brought to FCC this shift:
========================================================================
Accesses during shift:
Bob T, Steve Chappa work on power supplies, Bob T, Doug J
turn on PSs, start readout electronics....
Remove battery for EDM for charging.
========================================================================
Overview of shift:
No Beam for at least 24 Hours because of liquid helium
compressor problems. Ch 13 - Wed AM at the earliest

========================================================================
Description of Shift:

run spill time comment
------------------------------------------------------------------------
07:00 New shift arrives

07:50 One Shift member off to control. acc. exam.
08:30 and returns
09:30 Power supply work access, Bob T et al.
10:00 Test of site wide emergency warning system
Must go into the hall to hear it, or at least
open the door to the control room.
10:10 Fuse replaced in CsI supply, working again.
**** 10:30 DAJ swaps into access for Bob T
10:05 TeV has to purify. Expect been late Sat, or
early Sunday
11:15 Access done,spare power supply available
Tried to measure z's, but 12v battery low. Brought
it up for recharging.
14803 11:55 start cosmic run, no tapes or disk.
14:00 Do gas thing....
14:20 Hyperon99 organizing committee meeting ends
15:30 ahhhhh.... relief........
========================================================================
Follow up Notes on Previous Shift

========================================================================
Items to Follow up on Next Shift

** Going to 1 person shifts - work it out with who you are on shift
with for this cycle. Until this week end. See sep. message.

The problem of the inoperative xerox machine persists. It has been
suggested that this will be a part of the KAMI upgrade. However, we
hope for some kami beam just after the ketv run, so perhaps the
xerox upgrade could be moved forward to also be useful during
KTeV. Would that be spinn-on? ( if useful things coming after or
is spin-off? ).

Douglas Jensen DJensen@fnal.gov x8194