Re: Shift Summary for Eve shift, 08.31.99

Angela Bellavance (bellavan@rice.edu)
Wed, 1 Sep 1999 14:43:57 -0500 (CDT)

On Wed, 1 Sep 1999, Jim Graham wrote:

> Shift Summary for Eve shift, 08.31.99
>
> Hours of beam delivered at all intensities: 8.5
> Hours of beam delivered at nominal intensity: 8.5
> Hours of E832 data (special runs not included): 5.0
> Hours of special runs (laser scans, muon runs...): 0.0

Actually, while KTeV was in access, MCR had a ramp dump and beam was lost
for about 30 minutes. So the first two numbers should really be 8.0.
(Just trying to help :)

- Angela, MCR spy

_______
Angela Bellavance work: (630) 840-4144
bellavan@rice.edu home: (630) 548-3412
http://www.owlnet.rice.edu/~bellavan/ page: (630) 722-6861
"It has yet to be proven that intelligence has any survival value."
- Arthur C. Clarke